Key milestones / actions for the month
- VCAT Compulsory Conference 3rd December
- Construction contract review and negotiation
- Complete tender review and negotiate necessary inclusions (clarifications & purchaser changes)
- Commencement of demolition
Key Actions for following month
- Finalise contract sum
- Execute construction contract
- Complete demolition and undertake site condition report for handover to builder
PLANNING
Project set to be completed by July 2023.
CONSTRUCTION
Construction to commence April 2022.
SALES & MARKETING
A total of 4 apartments have been sold, a total of $7,695,000 in sales.