Stages 1 & 2a are well underway in development, with the civil construction team working efficiently to ensure the program is on track. The consultants across all divisions are confident that the first two stages will be complete by June 2022.
PLANNING
No significant changes to the town planning and design.
CONSTRUCTION
Works Completed in January:
– Commencement of Water main Installation
– Installation of Stormwater box culverts, high flow bypass, and outlets to retaining wall
– Commencement of excavation of retaining wall footings
– Stormwater installation of Line 13
MARKETING & SALES
Great overall response from December & January marketing campaign. The team have received an increase in leads and EOI’s over the last month mainly from the radio and television advertising, resulting in 5 new sales in January. The team are confident that sales will continue to increase this month.