Located in Shoal Point, Mackay Queensland. The project is scheduled to be constructed over 45 months with 8 separate land release stages. On completion the beachfront estate will consist of;
- 299 Residential lots & 80 Townhouses
- 5-star Resort
- Restaurants
- Supermarket
- Picnic areas
- Playgrounds
- Walking Trials
- Bike Riding Track
- Lakes
Planning
- Stage 2B designs have been submitted to Council for assessment.
- Concepts are currently being designed for the the 5-star resort and will then be submitted to Council for assessment.
- The design plans for the local neighbourhood park in Stage 2B to be lodged with Council for assessment.
Construction
Construction for Stage 1 & 2A on schedule to be completed by end of November 2022.
Marketing & Sales
The marketing team is continuing to ramp up the advertising on various mediums including social media, television, radio, and billboards across the Mackay region. The on site sales gallery is now open and has shown a great amount of interest.